Lagar & Förordningar är en kostnadsfri rättsdatabas från Norstedts Juridik där alla Sveriges författningar och EU-rättsliga dokument finns samlade. Nu kan organisationer och företag prova den mer omfattande juridiska informationstjänsten JUNO - gratis i 14 dagar - läs mer om erbjudandet och vad du kan få tillgång till här.

Judgment of the Court of 14 June 1990. - Commission of the European Communities v Italian Republic. - Obligation to provide the Commission with information - Non-fulfilment. - Case C-48/89.



European Court reports 1990 Page I-02425

Pub.RJ Page Pub somm



Summary

Parties

Operative part

Keywords



++++

Member States - Obligations - Implementation of directives - Failure - Justification - Not permissible

( EEC Treaty, Art . 169 )

Summary



As the Court has consistently held, a Member State may not plead provisions, practices or circumstances existing in its internal legal system in order to justify a failure to comply with the obligations and time-limits laid down in Community directives .

Parties



In Case C-48/89

Commission of the European Communities, represented by S . Fabro, a member of its Legal Department, acting as Agent, with an address for service in Luxembourg at the office of Georgios Kremlis, a member of its Legal Department, Wagner Centre, Kirchberg,

applicant,

v

Italian Republic, represented by Luigi Ferrari Bravo, Head of the Contentious Diplomatic Affairs Department of the Ministry of Foreign Affairs, acting as Agent, assisted by P . G . Ferri, avvocato dello Stato, with an address for service in Luxembourg at the Italian Embassy, 5 rue Marie-Adélaïde,

defendant,

APPLICATION for a declaration, pursuant to Article 169 of the EEC Treaty, that the Italian Republic has failed to fulfil its obligations under Council Directive 75/442/EEC of 15 July 1975 on waste ( Official Journal 1975, L 194, p . 39 ), Council Directive 76/403/EEC of 6 April 1976 on the disposal of polychlorinated biphenyls and polychlorinated terphenyls ( Official Journal 1976, L 108, p . 41, and Council Directive 78/319/EEC of 20 March 1978 on toxic and dangerous waste ( Official Journal 1978, L 84, p . 43 ) and Article 5 of the EEC Treaty

THE COURT

composed of : O . Due, President, F . A . Schockweiler and M . Zuleeg ( Presidents of Chambers ), G . F . Mancini, R . Joliet, T . F . O' Higgins, J . C . Moitinho de Almeida, G . C . Rodríguez Iglesias and F . Grévisse, Judges,

( the grounds of the judgment are not reproduced )

hereby :

Operative part



( 1 ) Declares that by failing to provide the plans and reports referred to in Articles 3(2 ) and 12 of Council Directive 75/442/EEC of 15 July 1975 on waste, Article 10 of Council Directive 76/403/EEC of 6 April 1976 on the disposal of polychlorinated biphenyls and polychlorinated terphenyls, and Articles 12(2 ) and 16 of Council Directive 78/319/EEC of 20 March 1978 on toxic and dangerous waste, the Italian Republic has failed to fulfil its obligations under those directives;

( 2 ) Dismisses the application in all other respects;

( 3 ) Orders the Italian Republic to pay the costs .